July 15, 2023
All updates to Duke Hill Park are complete!
July 13, 2023 update
A new Foot Golf course has been established.
July 11, 2023 update
The toddler play area at Duke Hill Park is nearing completion.
July 9, 2023 update
Swings in the toddler area are assembled.
June 30, 2023 update
New toddler climbing structures have been set into place.
June 26, 2023 update
Toddler play equipment is being installed at Duke Hill Park.
June 1, 2023 update
Crews are improving drainage at Duke Hill Park to prevent standing water and mitigate mosquitoes.
December 21, 2022 update
Swing set poles have been repainted and the new swings will be installed at Duke Hill Park.

December 10, 2022 update
The basketball court was painted with an art pattern.
November 15, 2022 update
The concrete slab has been poured and cured for the disc golf course.
November 15, 2022 update
The new climbing dome was installed and the mulch has been laid.
October 1, 2022 update
The new playground area has been installed at Duke Hill.